August 2019

Phase 3 is officially done!

May 2019

Phase 2 is officially complete! Phase 3 should be finished within the next few weeks. Starting tomorrow we will be using our main entrance.

April 2019

Just need some finishing touches on our new waiting room!

March 2019

We are heading into the final stretch of the project! Expected move in date is the beginning of April! Everything is coming together great!

January 2019

Phase 2 is looking good!

December 2018

Phase 2 is underway!

November 2018

We are excited to announce we are operating out of the new hospital wing. The old entrance is closed and the temporary entrance will be on the side. Thank you all for the support. We can’t wait until the next 2 phases are done!

October 2018

Grass seed is down!

September 2018

Siding and HVAC units are up!

August 2018

Roof is on! Starting the stone!

June 2018

Walls are going up!

May 2018

They poured the footers!

March 2018

We offically broke ground!

February 2018

Dr. Potorti and Dr. Kristi were busy this weekend at the Midwest Veterinary Conference in Columbus, Ohio. They were attending continuing education courses and looking at new and updated equipment for the upcoming hospital addition and renovation! We are so excited to be able to provide additional advanced diagnostics to our clients. Stay tuned! The digging will start in March!